Commissioning Procedure For Bus Ducts.

Electrical Bus Duct

Step by step Commissioning guidelines For Bus Ducts.

  1. Check the bus duct for physical damage and water ingress. Get it cleaned thoroughly.
  2. If a space heater is provided, ensure that there is adequate clearance between the heater wires and the main conductors. If necessary, dress the wires properly and securely.